guidelines:opm:close_out_project [2015/10/29 21:53]
cpn091020 [Procedure]
guidelines:opm:close_out_project [2019/07/30 19:37] (current)
Line 32: Line 32:
 | Close or change Purchase Orders | | | Close or change Purchase Orders | |
 | Remove unallowable after-term charges | | | Remove unallowable after-term charges | |
-| Confirm ​sub-recipients ​final invoices are paid | |+| Confirm ​subrecipients ​final invoices are paid | |
 | Confirm all adjusting financial entries are posted, including removal of overdrafts | | | Confirm all adjusting financial entries are posted, including removal of overdrafts | |
 | **From +45 days to + 90 days** || | **From +45 days to + 90 days** ||
Line 39: Line 39:
 | Confirm that financials and cost share reporting requirements are met | | | Confirm that financials and cost share reporting requirements are met | |
  
-OPM monitors ​the end dates to make sure the close-out process is commencing after the end date of the grant to make sure all expenses have cleared and been billed for. +OPM monitors end dates of Projects ​to make sure the close-out process is commencing after the grant deadline. Monitoring is done to ensure ​all expenses have cleared and have been billed for. 
-  * Valid expenses have 45 days to hit the Award after its end date and billed to the sponsor.  +  * Valid expenses have 45 days to hit the award after its end date and billed to the sponsor.  
-  * When all invoices are paid and necessary final financial reports are filed with the sponsor by the Office of Financeno later than 90 days or sooner if the contract requiresthe Sponsored Project ​is considered closed by OPM. +  * When all invoices are paid and necessary final financial reports are filed with the sponsor by the Office of Finance ​(no later than 90 days or sooner if the contract requiresthe sponsored project ​is considered closed by OPM. 
   * No additional notice is sent from OPM to Finance and the close-out is automatic based on the end date of the award+ 90 days.   * No additional notice is sent from OPM to Finance and the close-out is automatic based on the end date of the award+ 90 days.
   * Any overages are sent to the department so it can complete an IDT to remove those expenses from the grant.   * Any overages are sent to the department so it can complete an IDT to remove those expenses from the grant.
-  * Post-Award then changes the bill plan and revenue plan to "​completed"​ in order to change the contract line to "​closed"​. The project status is also changed to "​closed."+  * Post-Award then changes the bill plan and revenue plan to "​completed"​ in order to change the contract line to "​closed"​. The project status is also changed to "​closed"​.
   * OPM indicates on its weekly spreadsheet which grants have been processed through the close-out process as reference for the Office of Finance. The information includes:   * OPM indicates on its weekly spreadsheet which grants have been processed through the close-out process as reference for the Office of Finance. The information includes:
     * Name of PI     * Name of PI
Line 53: Line 53:
   * If the grant is deferred revenue, OPM indicates, in compliance with the award, whether the PI can keep any unspent funds or not.   * If the grant is deferred revenue, OPM indicates, in compliance with the award, whether the PI can keep any unspent funds or not.
     * If the PI can keep the funds, Finance transfers the unspent funds to the cost center indicated by the department.     * If the PI can keep the funds, Finance transfers the unspent funds to the cost center indicated by the department.
-    * By default, federal sponsors require the unspent funds be sent back. Finance processes a check and send it to the sponsor +    * By default, federal sponsors require the unspent funds be sent back. Finance processes a check and send it to the sponsor.
- +
-{{:​guidelines:​close-out-project.png?​nolink|}} +
  
 +{{:​guidelines:​opm:​screen_shot_2016-04-07_at_4.41.11_pm.png|}}
 === Related Policies and Procedures === === Related Policies and Procedures ===
  
Line 68: Line 66:
 If you have any questions regarding this procedure, contact Office of Post Award Management at ext. 4540 or via email at [[mailto:​kellymc@utdallas.edu|kellymc@utdallas.edu]]. If you have any questions regarding this procedure, contact Office of Post Award Management at ext. 4540 or via email at [[mailto:​kellymc@utdallas.edu|kellymc@utdallas.edu]].
  
 +Issued: June 2015